TL;DR
Walloon authorities ordered Google to suspend construction of a building at its planned data centre in Farciennes, saying it was built without proper planning permission. Google says work has paused while it awaits guidance; the company has also challenged a separate refusal to change the site’s cooling plan, with a court hearing scheduled for January.
Walloon authorities have ordered Google to suspend construction on a building at its planned data centre in Farciennes, Belgium, saying the three-hectare structure lacked proper planning permission. Google says it has paused the work pending further guidance. The dispute also involves a refused request to change the site’s cooling system to use water from the nearby River Sambre.
Regional inspectors visited the site on Thursday and told Google representatives to halt construction, the regional authority said. On Friday, Nicolas Yernaux, a spokesman for Wallonia, described the work as “a major offense” and said the building had been constructed illegally, AFP reported. The order concerns one building, not the entire data centre site.
Google told the BBC that work had been paused “pending additional guidance.” The company also said it had operated in Belgium for more than 15 years and remained “committed to complying with local laws.” Greenpeace Belgium said this week that drone footage showed construction continuing, but that allegation is distinct from a court finding. The authorities’ order and its stated reason have been reported through official statements; the order itself was not found online by the source report.
The cooling dispute is related but separate. The project originally planned to use air cooling, according to Belgian media cited by AFP. Google later applied to switch to a system using water from the Sambre. Regional officials refused that application over the summer amid concerns about water use and drought. Google has challenged the refusal in court, and AFP reported that a hearing is scheduled for January.
Stop-work order · court hearing pending
How a cooling plan became a stop-work order
At the heart of the row is water: how the computers are cooled, and where the water comes from.
- The planAir coolingThe original project planned to cool the computers with air, Belgian media reported.
- The changeRiver waterGoogle applied to cool the site with water from the nearby River Sambre.
- SummerRequest refusedAfter a dry spring, regional officials refused the change. Google went to court.
- This weekStop-work orderInspectors told Google to halt building. Officials call it a major offence.
- NextCourt in JanuaryGoogle says it paused the works and will follow local laws.
- Blue: the former mining site, some 50 hectares.
- Orange: the building of three hectares that officials say lacks proper permission.
Sources: AFP, as published by Arab News, November 27, 2026; BBC News, November 29, 2026. Schematic.
Graphic: Powered by Thorsten Meyer AI
Permits Put Data Centre Plans at Risk
The halt shows how planning approvals can directly affect construction timelines for large digital infrastructure projects. A stop-work order can delay a facility intended to support cloud computing and AI services, even as demand for that capacity grows. The scale of any delay to Google’s plans in Farciennes has not been reported.
The dispute also brings local concerns about water, land use and environmental oversight into a project tied to the expansion of data centres. Cooling choices can have different resource demands, but available reports do not state how much water Google proposed to draw from the river. The case therefore highlights the questions facing local authorities without establishing the project’s specific water impact.
For residents, the immediate issue is whether construction complied with the permits in force. For Google and other infrastructure developers, the case is a reminder that a change in design or a disputed building permit can affect a site’s schedule. It does not, by itself, show that the Farciennes project has been cancelled or that all of its construction is prohibited.
Popular right now

Roborock F25 GT Gen 2 Cordless Wet-Dry Vacuum Mop

Ninja Kitchen System Pro BL770, 1500W Blender and Food Processor Combo

KitchenAid 5.5-Quart Bowl-Lift Stand Mixer, Porcelain White
As an affiliate, we earn on qualifying purchases.
The River Sambre Permit Dispute
The data centre is planned for a former mining site of about 50 hectares, according to AFP. The building cited by regional authorities covers three hectares. A comparison in the source report puts that area at roughly four football pitches; the comparison is illustrative, not a measure of the whole project.
Google’s request to change the cooling plan was refused during the summer. AFP reported that severe drought conditions since spring heightened concerns about taking water from the river. Greenpeace Belgium said the latest version of the planning permission had been revoked in August and alleged that work continued afterward. Authorities subsequently ordered the halt. Those details describe the sequence reported by the cited sources; the legal status of the building remains contested.
The Farciennes dispute comes amid scrutiny of data centre development elsewhere. AFP reported that Finnish authorities halted work at two Google data centre sites in October. That is a separate case and does not determine the outcome in Belgium.
“We have operated in Belgium for over 15 years and remain committed to complying with local laws.”
— Google, in a statement reported by the BBC
Legal Status of the Building
It is not yet clear whether the building can be legalised, how long the stop-work order will remain in place, or whether Google will be allowed to resume construction before the court considers the cooling-permit dispute. The order itself was not available online in the source report, and the public reporting does not provide its full terms.
The authorities’ allegation that the building lacked proper permission should not be treated as a final judicial finding. Google’s challenge to the refusal of its cooling-plan application is also unresolved. Reports do not specify the proposed volume of water use, the full technical design, or the likely schedule impact on the wider data centre project.
January Hearing and Site Status
The next reported milestone is a court hearing scheduled for January on Google’s challenge to the regional refusal of its cooling-plan application. That case concerns the proposed use of river water; the available reports do not say whether it will also settle the separate planning-permission issue behind the construction halt.
For now, Google says work is paused, while Walloon authorities’ order stands according to the reporting available on November 29. Further information from the court, regional officials or Google may clarify whether the building can be regularised and when, if at all, work may restart.
Key Questions
Regional authorities said a three-hectare building at the Farciennes site was being constructed without proper planning permission. They described the alleged violation as a major offense.
Has Google stopped work at the site?
Google told the BBC that work had been paused pending additional guidance. The stop-work order applies to the building identified by authorities; reports say it does not cover the entire site.
What does the River Sambre have to do with the dispute?
Google applied to change the planned cooling system from air cooling to one using water from the River Sambre. Regional officials refused that request over the summer, citing concerns reported amid drought conditions. Google has challenged that refusal in court.
When will the dispute be considered in court?
AFP reported that a hearing on Google’s challenge to the cooling-plan refusal is scheduled for January. The available reports do not establish whether that hearing will decide the separate construction-permission issue.
Has the Farciennes data centre project been cancelled?
No cancellation has been reported. Authorities ordered construction on one building to stop, and Google says work is paused. The project’s longer-term status and construction timeline remain unclear.